As per SEBI's guidelines, DP is required to process the demat request received by it within 7 days. Further, issuer company / its RTA may take up to 15 days to process the demat request received by them. Considering the time required for transmission of documents from DP to issuer company / RTA, dematerialization will normally take about 30 days.